Current Projects
LDFA 6
Bond payments began in 2016 and will extend to 12/2040. These payments are the result of debt issuances tied to the water and wastewater services which were extended to the property.
Accomplishments
LDFA 6
Water service was extended from the City to the LDFA district. A forced main sanitary line was constructed from the District to the Coldwater wastewater reclamation facility, and Fiske Road was extended from Newton Road to Jonesville Road.
- 4.5 miles of water main
- 6 miles of sanitary forced main
- 1 mile of road extension
- 1 new electrical substation
- Upgrades at Wastewater Treatment Plan
Unspent Revenues
LDFA 6 will receive monthly revenue from the Lakeland Correctional Facility until 2026 as a result of the facility's connection to the LDFA sewer line. These funds will not be comingled with the standard revenues that are collected for the purpose of making debt payments. Rather, they will be saved and can be used on future infrastructure work within LDFA #6.